[:en]Residence WiFi renewal project[:af]Koshuis WiFi-hernuwingsprojek[:]

[:en]

Over the past two years Information Technology’s network infrastructure team worked hard at ensuring that all SU campus residences are equipped to provide effective WiFi network access to students.

As the project is drawing to a close, we can recap and provide statistics.

Nearly 1500 WiFi access points were installed of which 571 over the December/January holidays. The last, outstanding WiFi hotspots will be installed during the June/July holiday time period.

The following number of WiFi hotspots were installed over the holidays:

Stellenbosch campus:

Huis De Villiers               67

Dagbreek                          89

Metanoia                          186

Huis McDonald               37

Helderberg installations will be completed at the end of February while Minerva is scheduled for the June 2020 slot. Due to construction at Goldfields installing WiFi points wasn’t possible, but is scheduled for when construction is completed. For more detail on current WiFi coverage on Stellenbosch campus, see below.

Tygerberg campus:

Franci van Zyl                  67

Hippokrates                     78

Elective students            15

Meerhof is currently being completed.

Worcester campus:

WiFi for whole building has been revamped  32

 

 

 

[:af]

Informasietegnologie se netwerk-infrastruktuurspan het oor die afgelope twee jaar hard gewerk om te verseker dat alle koshuise op US-kampusse voldoende toegerus is om effektiewe WiFi netwerktoegang aan studente te verskaf. 

Soos die hernuwingsprojek einde se kant toe staan kyk ons na wat ons bereik het en ’n paar syfers verskaf. 

Bykans 1500 WiFi-toegangspunte is geïnstalleer waarvan 571 oor die afgelope Desember/Januarie vakansie. Die laaste, uitstaande WiFi-punte sal gedurende die Junie/Julie vakansie installeer word. 

Die volgende aantal WiFi-punte is oor die vakansie installeer: 

Stellenbosch-kampus:

Huis De Villiers               67

Dagbreek                          89

Metanoia                          186

Huis McDonald              37

Helderberg se installasies sal voltooi word teen die einde van Februarie, terwyl Minerva geskeduleer is vir Junie. Weens konstruksie was installasies by Goldfields nie moontlik nie, maar is dit geskeduleer vir wanneer konstruksie voltooi is. Vir meer detail oor WiFi-dekking op Stellenbosch-kampus, sien die kaart onder. 

Tygerberg-kampus:

Franci van Zyl                   67

Hippokrates                     78

Elektiewe studente         15

Meerhof word tans voltooi.

Worcester-kampus:

WiFi vir die hele gebou is opgeknap  32

 

 

[:]

Comments are closed.